Project Risk Management Essay

2056 words - 9 pages

PM 595-Project Risk Management
November 2010-Section A
Project Part I

Grayson Cash

TCO A

Identifying Project Risks

The process for risk identification for a second Oresund Bridge would involve plan for risk management. This would involve first the secure risk management plan in place. This would involve meetings to clearly define the scope of the project. A second bridge and its usefulness, cost, and scheduling will be primary factors of interest. But another area would be in the enterprise environmental factors. These factors specifically are organizational structure, government/industry standards, infrastructure*, existing human resources, company work ...view middle of the document...

Categorizing Project Risks

The categorization of project risks is aforementioned. Categorization should be based on scope, schedule, and cost. Yet it should journey further in the areas of technical issues, project management risks, organizational risks, external risks, historical information, project files, and published information. With respect to the project, the technical issues would have to do with the design and production of the bridge with respect to the current one. Efficiency, traffic, and structure will be focal points of interest. The project management risks are what could go wrong within its process of planning and control processes to monitor and maintain tasks. The organizational risks for the second Oresund Bridge would be resources and lack of top-level management support that could be a factor. The external risks would have to do with the economics surrounding the business or global interests. In the first project funding was in the form of a loan to be paid back over 25 to 30 years. With the global economy in 2010, this might be an issue when funds could be utilized in other areas. The lessons learned will be useful as in the first project they were able to deliver 5 months ahead of schedule and under budget. The project files could be useful but technical information in manuals would probably be not as useful as we are creating a project not necessarily in a manual.

Ranking Project Risks
The ranking of project risks would be the use of quantitative and qualitative analysis, sensitivity analysis, a decision tree, and a risk matrix. The usefulness of the risk matrix would be to assist in knowing the probability rating assigned for each risk whether it is under scope, schedule, and cost. With respect to the project every risk noted above would fall into a ranking of probability. Once that is completed, we could look at its sensitivity to analyze the sensitivity of risks affecting the risks noted. From there we could do further quantitative and qualitative analysis. These analyses will ensure we could whittle down the risks to an even lesser amount of risks to address an account for. The decision tree would allow for a visual for where we want to do in direction should events arise and how we could address it. The ranking is thus important for many reasons but overall mostly to deal with risk before they should arise.

TCO C

Identifying Key Decision Paths & Options

Identifying key decisions and paths for the Oresund project start with identifying the goals and objectives by determining the best possible outcome. The process should begin with a WBS to assign estimated time to complete activities listed. Then the estimated based on prior project experience along with historical data to help shape the information gathering. Reviewing the historical data and lessons learned will serve as a template for the process. A checklist based on what was gathered in the first project...

Other Papers Like Project Risk Management

Mba 590 Managing Project Risk Essay

4119 words - 17 pages Running head: Implementation Plan Research Managing Project Risk Research Paper Jacquelyn Burton, Brittany Wyatt, Jamie Luce and Harold Pitner MBA590 Strategic Implementation and Alignment Dr. Kathryn Moland April 30, 2008 Implementation Plan Research Managing project teams can be a very tedious task. There are many concepts in this week’s reading that conveyed this fact. Effective leadership, ethics, and

Preliminary Risk Valuation in Indonesia Coal Bed Methane Project (Case: Pertamina Cbm Project)

1164 words - 5 pages PRELIMINARY RISK VALUATION IN INDONESIA COAL BED METHANE PROJECT (Case: PERTAMINA CBM Project) DEWI GENTANA & DEDI YUSMEN PERTAMINA CBM TEAM Gas Asia Conferences, Kualalumpur 17-18 March 2009 OUTLINE A. RISK VALUATION APPROACH & METHODOLOGY B . SUB SURFACE, SURFACE, ECONOMICS C . RISK VALUATION RESULT AND ANALYSIS D. CONCLUSION Gas Asia Conferences, Kualalumpur 17-18 March 2009 1 OVERVIEW Overlapping Oil and Gas

Risk Management Plan

998 words - 4 pages 10/10/2014 IS110 Risk Management Project Part 1 Introduction Purpose of the Risk Management Plan A risk in an event or condition that, if it occurs, could have a positive or negative effect on your project’s objectives. Risk Management is the process of identifying, assessing, responding to, monitoring, and reporting risks. This Risk Management Plan defines how risks associated with the Defense Logistics Agency project will be identified

Risk Management In Projects

3771 words - 16 pages Table of Content 1. Introduction 2 2. Project Management 3 2.1 Definition of Project Management 3 2.2 Advantages and Disadvantages in Project Management 5 2.3 Success Factors in Projects 6 2.4 Control Project Progress 7 3. Project Risk Management 8 3.1 The Risk Management Process 8 3.2 Definition of Risk 10 3.3 Managing Risk 10 3.4 Identify Risks 11 3.5 Risk Quantification 14 3.6 Plan Risk Response

Mis Fnb Project

1396 words - 6 pages – Key Elements of Project Management – Project Lifecycle Phases – Project Management Functions Office of the Senior Associate Vice President for Finance 3. Project Participants – – – – Project Stakeholders Project Sponsor & Owner Project Manager Project Team 4. Basic Project Tools – – – – Project Charter Project Management Plan WBS / Schedule Action / Risk / Change Tracking – Document Management Page 4

Project Management

745 words - 3 pages for project management includes the project stakeholders, project management knowledge areas, and project management tools and techniques. The 10 knowledge areas are project integration management, scope, time, cost, quality, human resource, communications, risk, procurement, and stakeholder management. • Project integration management is an overarching function that affects and is affected by all of the other knowledge areas. Project management

Risk Management

2511 words - 11 pages Impact of Risk Management in Application Development Abstract: Nowadays, software is becoming a major part of enterprise business. Software development is activity connected with advanced technology and high level of knowledge. Risks on software development projects must be successfully mitigated to produce successful software systems. Lack of a defined approach to risk management is one of the common causes for project

Project Basics

868 words - 4 pages PLAN 9 3.3 CHANGE MANAGEMENT PLAN 9 3.4 ISSUE MANAGEMENT PLAN 9 3.5 RISK MANAGEMENT PLAN 9 APPENDIX 10 A – REVIEW TEAM 10 B – COMMUNICATIONS PLAN 10 C – QUALITY MANAGEMENT PLAN 10 D – CHANGE MANAGEMENT PLAN 10 E – ISSUE MANAGEMENT PLAN 10 F – RISK MANAGEMENT PLAN 10 1. Project Plan Overview and Critical Assumptions The purpose of the Project Plan is to present the detail required to successfully execute and control the project

Case Study

616 words - 3 pages case, risk analysis, and availability of necessary resources (e.g., money, people with correct competencies).  Politics exist in any life cycle phase of a project. Two or more people or a group of people is needed for a politics to occur. Politics in project management have positive impact and negative impact in a project management. Project manager using his political influence with project sponsor to get qualified resources needed or a high

Lessons Learnt Report

2626 words - 11 pages MIS Project Management at First National Bank Lessons Learned Report Prepared by: Group B 09-12-2013 Table of Contents 1. Introduction 3 2. Project Overview 4 3. Contributing Factors to Failure 5 3.1. Project Proposal Lifecycle 5 3.2. Planning and Communications 6 3.3. Risk Management 6 3.4. Stakeholder Involvement 7 4. Recommendations 9 4.1. Inter-Departmental / Stakeholders Conflict

Analysis of the Components of Project Portfolio Management and Impact on Project Managers

834 words - 4 pages pipeline flow, project prioritization, change management, resource management, portfolio evaluation and risk management. The objective is to ensure that the strategic business objectives such as revenue growth, cost reduction, regulatory mandate, business continuity, among others, are achieved. Key Components of project portfolio management Strategic pipeline flow. This component includes the processes of screening of project proposals and

Related Essays

Project Risk Management Essay

1020 words - 5 pages Eric Bani Professor James Young “Politics, Institutions, and Project Finance: The Dabhol Power Project. Strayer University 2011 Project risk management has been identified as the number one cause of project failure by most if not all organizations. In view of that project risk management is given prominent place in any project undertaken by businesses. Project managers are therefore are under immersed pressure to practice the best

Project Risk Management Paper

2285 words - 10 pages Course Project Project Risk Management Contents Introduction 4 Statement of work 5 Statement of Work—Project Description and 6 WBS 8 Risk Analysis and Probability Matrix – Qualitative Analysis 10 Risk Register 11 Decision Tree 11 Decision Tree Analysis 11 Fault Analysis Tree 12 Fault Tree Analysis Summary 12 Conclusions 13 Works Cited 13

Is3110 Project: Risk Management Plan Essay

1807 words - 8 pages milestones (POAM). Scope: Risk assessment is used in every career and on every project in all fields of study. There are different types of risks involved depending on what you are doing. An architect has to assess all risks involved with weather, natural resources they may run into underground, the slightest miscalculation could throw the entire project off! Networking security personnel play a major role in the security of anything and

Risk For Project Example Essay

1894 words - 8 pages Payam Banikarimi Course Project Risk Plan As we know there are some uncertain events that can impact to the project objective that called Risk. Therefore, I consider the following set of process that Risk Management must do these. Overall, Risk management should involve identifying, assessing, and responding to project risks in order to minimize the likelihood of the potential impact of the events on the accomplishment