This website uses cookies to ensure you have the best experience. Learn more

Project Management Chapter 6 Essay

723 words - 3 pages

Chapter 6 Assignment
2. According to the book, the best option for someone just starting a project for the first time and if it’s small would be the activity-on-the-arrow diagramming, because each element is represented with a different symbol. I, personally, think that the activity-in-the-box approach is all so usable because the words are boxed off, so you are not going to get things mixed up that easily, unless you are stupid, just saying.
3. Alright, this was a little difficult. I will attempt to explain my findings. I figured the following:
* Earliest start time: 19 days
* Earliest finish time: 18 days (how this happened, I don’t know)
* Latest start time: 47 days
* Latest finish time: 47 days
I found the latest ones by adding the activities one by one, assuming that would take the longest, in order, of course. Like a to b, b to ...view middle of the document...

1 day later, D moves to G and H (E 2, I 5)
5. 2 days later, E moves to H (I 3, G 3, H 4)
6. 3 days later, I goes to finish, G moves to J (H 1)
7. 1 day later, H moves to J (J 3)
8. 3 days later J goes to finish
So added up it equals 18 days.

From finish to start:
1. After 4 days, J moves to G and H
2. 2 days later, I moves to F (G 3, H 4)
3. 3 days later, G moves to D (H1, F1)
4. 1 day later, H moves to D, E & F moves to B, C
5. 4 days later, F moves to C, B & D moves to A (E 2)
6. 2 days later, E moves to A (C 1, B 2, A 3)
7. 1 day later, C moves to A (B 1, A 2)
8. 1 day later, B goes to start (A 1)
9. 1 day later, A goes to start

Added up this equals 19 days.

7. Task F does not overlap C and D because they are its predecessors and that would be impossible. Task F overlaps task E because task E takes 14.33 days to complete and task F’s predecessors finish before task E finishes, so F starts before E finishes.
* If task C and D were the same length, the time to complete the project would either take longer or stay the same depending on which task length you picked to change. If they were both changed to 12.33 days, the time would be increased because task G can’t start until task D is finished and task H cannot start until task G is finished.
* If task C and D were both changed to the duration of 6 days each then the times would stay the same, because it would only be task C changed and the only thing that would be shortened by that is the starting time of task F and task F is not a predecessor of any other task.

Case Study: Springville
1. I would use the Gantt chart because I am the most acquainted with it at this point and because it includes all of the criteria that everyone wants. It is easy to use, shows the duration of tasks, shows milestones, everyone can see the flow of work, they can see the sequence of events, they can depict which tasks can be undertaken at the same time, and they can tell how far tasks are from completion.

Other Papers Like Project Management Chapter 6

Cost Management Essay

1788 words - 8 pages staff acquisition or through procurement. We’ll cover staff acquisition in Chapter 9 and procurement in Chapter 12. Figure 7-2 is a recap of all the inputs, tools, and techniques, and outputs of resource planning. 6 Chapter 7: Introducing Project Cost Management CertPrs8 / PMP Project Management Professional Study Guide / Phillips / 223062-2 / Chapter 7 FIGURE 7-1 Project management software can assist in resource planning. P: staff acquisition or through procurement. We’ll cover staff acquisition in Chapter 9 and procurement in Chapter 12. Figure 7-2 is a recap of all the inputs, tools, and techniques, and outputs of resource planning. 6 Chapter 7: Introducing Project Cost Management CertPrs8 / PMP Project Management Professional Study Guide / Phillips / 223062-2 / Chapter 7 FIGURE 7-1 Project management software can assist in resource planning. P:\010Comp10Comp

Enterprise Project Management Essay

599 words - 3 pages at once an EPM practice is ideal in dealing with uncertainty and constraint. References: Schwalbe, K. (2011) Information Technology Project Management 6th Ed. Course Technology, Cengage Learning Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide), Fourth Edition (2008). Burke, E. (2002) “Project Portfolio Management,” PMI Houston Chapter Meeting. Besner, C. and Hobbs, B. (2006)., “The

Mgmt340 Chapter 3, 4

615 words - 3 pages Chapter 3: Problems 2 & 4 2. What are some sources of risk in a systems analysis and design project, and how does a project manager cope with risk during the stages of project management? 2. Some sources of risk in a systems analysis and design project are resources, current technology, and rules and regulations. Sometimes, resources are not always available whether it be manpower or materials and software. Current technology can

Discussion Questions

825 words - 4 pages importance of top management commitment and the development of standards for successful project management. Provide examples to illustrate the importance of these items based on your experience on any type of project. 6. What are the phases in a traditional project life cycle? How does a project life cycle differ from a product life cycle? Why does a project manager need to understand both? 7. What makes IT projects different from other types

Study Guide Cis 3001

2323 words - 10 pages Chapter 1: The Nature of Information Technology Projects What is the current state of IT projects? What are key factors for successful IT projects? Hint: Refer to the summary of CHAO study IT Projects are showing higher success rates. Better project management tools & processes, smaller projects, improved communication among stakeholders, more skillful IT project managers What are four different approaches to improving the

Chapter 6 Review Questions

541 words - 3 pages Miguel Berrios July 28, 2013 Chapter 6 Review Questions 1. How does the WBS differ from the project network? The WBS differs from the project network in several ways. The WBS is hierarchical while the project network is sequential. The work packages of the WBS are identified independently of other work packages, have definite start and finish points, require specific resources, include technical specifications and

Prince2 - Project Management Team Roles

3577 words - 15 pages support and advice required for the management, planning and control of the project be responsible for project administration liaise with any Suppliers or account managers.               C.6 Team Manager The use of this role is optional. The Project Manager may find that it is beneficial to delegate the authority and responsibility for planning the creation of certain products and managing a team of specialists to produce

Project

3660 words - 15 pages Breakdown Structure. Finally, the chapter is concluded with a discussion of multidisciplinary teams including the topics of integration management and concurrent engineering. Cases and Readings Some cases appropriate to the subject of this chapter are: Harvard: 9-692-058 Taco Bell Corp. This 31-page best-selling case describes a project to implement a new strategic plan involving major changes in layout, staffing, quality, product design, and

Project Management Is An Art Form NOT A Science

1206 words - 5 pages manage complex projects. Bibliography: Kate Belzer (2004) Project Management: Still More Art than Science Andrew D. Brown, Matthew R. Jones (1998) Doomed to failure: narratives of inevitability and conspiracy in a failed IS project. Organization Studies, Winter. Michael Greer (1999) 14 Key Principles for PM Success. Chapter 6: Planning and Managing Human Performance Technology Projects, "Handbook of Human Performance Technology

Network Managent It245 Ip

384 words - 2 pages IP3: TSD NETWORK MANAGEMNT GUIDE IT245-1404B-01: INTRODUCTUCTION TO NETWORK MANAGEMENT INSTRUCTOR: RODNEY BROWN 1 DECEMBER 2014 TABLE OF CONTENTS CHAPTER 1 2 1.1 ORGANIZATION DESCRIPTION 2 1.2 NETWORK SERVERS 2 1.3 NETWORK PERSONNEL RESPONSIBILITIES 2 CHAPTER 2 4 2.1 NETWORK ARCHITECTURE 4 2.2 NETWORK DIAGRAM 5 CHAPTER 3 6 3.1 ORGANIZATION DESCRIPTION 2 3.2 NETWORK

Project Resource Allocations

3058 words - 13 pages contribution to the projects and can monitor implementation and outcomes. This guide has the follow ing sections: Chapter 1: Technical aspects to project management What is a project? What is project management? Project stakeholders T he project life cycle Defining the project o Defining the project scope o Creating the work breakdown structure o Estimating cost and developing budget Constructing a project network plan o Project schedule Chapter 2

Related Essays

Project Management | Chapter 01 Essay

645 words - 3 pages 8/23/2013 Student Version CHAPTER ONE What is a Project? • Project Defined –A complex, nonroutine, one-time effort limited by time, budget, resources, and performance specifications designed to meet customer needs. Modern Project Management McGraw-Hill/Irwin • Major Characteristics of a Project –Has an established objective. –Has a defined life span with a beginning and an end. –Requires across-the-organizational participation

Chapter 6 Foundations Of Business Intelligence: Database And Information Management

3513 words - 15 pages )                                           Chapter  6   Foundations  of  Business  Intelligence:  Database  and  Information   Management     • • Effective  IS  provides  accurate,  timely  and  relevant  information   Often:  poorly  organized  and  maintained  data     File

Ungs2050 Essay

418 words - 2 pages Calendar Overall for Case-Study Presentation & Mid-Term Exam – MGT 4760 (Strategic Management) Sem 1, 2012/2013 Sec 8 (M-W) No. | Week | Topics | Class Day | Date | Schedule | Details | | 1 | Chapter 1: The Nature of Strategic Management | 1- Mon 2- Wed | 10/912/9 | | | | 2 | Chapter 2: The Business Vision and Mission | 3- Mon 4- Wed | 17/919/9 | | | | 3 | Chapter 3: The External Assessment | 5- Mon 6

Project Management Competencies In The Project Oriented Organization

3909 words - 16 pages organization. Source: People in Project Management Copyright: Roland Gareis and Martina Huemann Copyright statement This white paper is a chapter taken from a Gower book and provided free of charge to visitors to the website of the National Centre for Project Management. You may download it freely from the website www.cs.mdx.ac.uk/ncpm/about.html. You may also share it with colleagues, either in printed or electronic form (via e-mail), as long as