Critical Path Essay

1509 words - 7 pages

Critical Path Analysis & PERT Charts
Planning and scheduling more complex projects The benefit of using CPA over Gantt Charts is that Critical Path Analysis formally identifies tasks which must be completed on time for the whole project to be completed on time, and also identifies which tasks can be delayed for a while if resource needs to be reallocated to catch up on missed tasks. The disadvantage of CPA is that the relation of tasks to time is not as immediately obvious as with Gantt Charts. This can make them more difficult to understand for someone who is not familiar with the technique. A further benefit of Critical Path Analysis is that it helps you to identify the minimum length of ...view middle of the document...

The chart is repeated in figure 1 below: Figure 1. Task List: Planning a custom-written computer project NB: The start week shows when resources become available. Whether a task is parallel or sequential depends largely on context. Task Possible Length start week 1 week 1 week 3 week 1 week 1 week 4 5 days 1 day 2 weeks 2 weeks 2 weeks 3 weeks Type Dependent on...

1. High level analysis 2. Selection of hardware platform 3. Installation and commissioning of hardware 4. Detailed analysis of core modules 5. Detailed analysis of supporting utilities 6. Programming of core modules

sequential sequential 1 parallel 2

sequential 1 sequential 4 sequential 4

7. Programming of supporting modules week 4 8. Quality assurance of core modules 9. Quality assurance of supporting modules 10.Core module training 11.Development of accounting reporting 12.Development of management reporting 13.Development of management analysis 14.Detailed training 15.Documentation week 5 week 5 week 7 week 6 week 6 week 6 week 7 week 4

3 weeks 1 week 1 week 1 day 1 week 1 week 2 weeks 1 week 2 weeks

sequential 5 sequential 6 sequential 7 parallel parallel parallel 6 5 5

sequential 5 sequential 1-13 parallel 13

2. Plot the activities as a circle and arrow diagram Critical Path Analyses are presented using circle and arrow diagrams. In these, circles show events within the project, such as the start and finish of tasks. Circles are normally numbered to allow you to identify them. An arrow running between two event circles shows the activity needed to complete that task. A description of the task is written underneath the arrow. The length of the task is shown above it. By convention, all arrows run left to right. An example of a very simple diagram is shown below:

This shows the start event (circle 1), and the completion of the 'High Level Analysis' task (circle 2). The arrow between them shows the activity of carrying out the High Level Analysis. This activity should take 1 week. Where one activity cannot start until another has been completed, we start the arrow for the dependent activity at the completion event circle of the previous activity. An example of this is shown below:

Here the activities of 'Selecting Hardware' and 'Core Module Analysis' cannot be started until 'High Level Analysis' has been completed. This diagram also brings out a number of other important points: • • • Within Critical Path Analysis, we refer to activities by the numbers in the circles at each end. For example, the task 'Core Module Analysis' would be called 'activity 2 to 3'. 'Select Hardware' would be 'activity 2 to 4'. Activities are not drawn to scale. In the diagram above, activities are 1 week long, 2 weeks long, and 1 day long. Arrows in this case are all the same length. In the example above, you can see numbers above the circles. These show the earliest possible time that this stage in the project will be reached. Here units are whole weeks.

A different case...

Other Papers Like Critical Path

Red Zuma 2 (Resource Allocation) Essay

588 words - 3 pages | Detailed Marketing Plan | 179 | 134 | 1.6 | Manufacturing Process | 55 | 0 | 1.9 | Lab Test Prototypes | 9 | 0 | * The four Marketing Specialists are no more over-allocated. * All the tasks having slack (in the initial schedule) have been re-scheduled for resource leveling. 3. Impact of leveling within slack The ‘Manufacturing Process task’ and ‘Lab Test Prototype task’ do not have slack and are now on the critical path. Since

Huntsville Plant Essay

852 words - 4 pages | Huntsville Plant Project | Erika Moore Project Management 586 | Erika Moore 9/22/2013 | First, let’s start with a simple question. What is a critical path? According to Gido (2015), “In large network diagrams, there may be many paths of activities from the project start to the project completion. The Critical Path is the longest containing the most time consuming activities” (p. 157). Now that we have an understanding of

Business Management

2509 words - 11 pages 1) Please identify the critical path using the activity letter provided and explain the significance of the critical path. The QSB output below shows the critical path. The path is significant because it demonstrates the path that is the most time consuming (longest to finish), as the activities on the critical path have no slack. The completion of each activity in this sequence is critical to the start of the next activity in the sequence

A&D High Tech

1302 words - 6 pages FRI 11/21/13 (total duration of 130 days). (MS Project 2007) 2. What is the total cost? How much of the total cost are labor costs? Capital costs? Total Cost: $98,500 + $844,980 = $943,480 Labor Cost: $ 844,980 (given result of project) Capital Cost: (12 Windows 2000 workstations*$3,000) + (5 Window 2000 servers*$12,500) = $98,500 3. What is (are) the critical path(s) in the project? What is the level of risk in completing tasks on

Pert Analysis in Management Sceinces

5340 words - 22 pages Results …………………………………………………….. 15 4.4 Recommendations ………………………………………………………... 16 4.5 Conclusions ………………………………………………………………. 16 4.6 Acknowledgement ………………………………………………………... 17 4.7 References ………………………………………………………………... 17 Abstract PERT (Project Evaluation and Review Technique) followed by CPM (Critical Path Method) is a method of

Critical Chain

2032 words - 9 pages not happen soon, then what the business schools teach their learners will soon be obsolete (Goldratt, 1997). The focus of the book is the shift of project management from the critical path method to the critical chain method of project management. Likewise, the focus of this paper shall be to show the necessity for the shift from the critical path method to the critical chain method and its comparative advantage to the process that is project

Cpm and Pert

2966 words - 12 pages Table of Contents 1.0 INTRODUCTION 3 2.0 NETWORK TECHNIQUES 7 2.1 Introduction 7 2.2 Critical Path Method (CPM) ……………………………………………………………..…………………………………… 8 2.2.1 Steps of CPM Project Planning ……….……………………………………………………………………………… 9 2.2.2 Example of CPM …………………………………………………………………………………………………………… 11 2.2.3 Benefits of CPM …………………………………………………………………………………………………………… 12 2.2.4 Limitation of CPM

Wgu Qat1 Task 4

893 words - 4 pages completing the activity on an accelerated basis (crash cost). Task: A. Use the estimates for Company A in Table 1.1 to do each of the following: 1. Determine the expected completion time for each of the ten project activities, showing all your work. a. Determine the variance for each project activity, showing all your work. 2. Prepare a PERT chart (network diagram) to identify the critical path for project completion. 3

Quantitative Analysis

1119 words - 5 pages PERT/CPM TECHNIQUES Introduction: This task requires candidates to prepare a program evaluation and review technique (PERT) chart and apply critical path method (CPM) techniques. Given: Company A is installing a Web-based customer-feedback system to meet customer needs for quick response when rolling out new products. A new product line is rolling out in 34 weeks and the customer-feedback system must be installed and running in time for

Critical Thinking

563 words - 3 pages what we do in our daily lives depend on the effectiveness of our thoughts, morally and immorally. Critical Thinking Critical thinking is a path of freedom from half-truth and deception. A person has the right to question everything that sees, hear and read as well a process though which one solve problems and makes decision, it involves self-discipline and structure, acquiring this ability is a major goal of college education. Critical

Proj586 W3 Homework Aib Solutions

663 words - 3 pages Scheduled Completion of the Project? (5 points) Answer: 32 days b) What is the Critical Path of the Project? (5 points) Answer: B-D-F-G-I c) What is the ES for Activity D? (1 points) Answer: Day 6 d) What is the LS for Activity G? (1 points) Answer: Day 15 e) What is the EF for Activity B? (1 points) Answer: Day 6 f) What is the LF for Activity H? (1 points) Answer: Day 32 g) What is the float for Activity I? (1 points

Related Essays

Critical Path Essay

634 words - 3 pages points) 32 Days b) What is the Critical Path of the Project? (5 points) B, D, F, G, I c) What is the ES for Activity D? (1 points) Day 6 d) What is the LS for Activity G? (1 points) Day 15 e) What is the EF for Activity B? (1 points) Day 6 f) What is the LF for Activity H? (1 points) Day 32 g) What is the float for Activity I? (1 points) 0 Days Problem 2 The following data were obtained from a project to

Critical Path Whistler Ski Resort Essay

1040 words - 5 pages Sustainable Companies Sustainable development is a concept that looks to meet “the needs of the present without compromising the ability of future generations to meet their own needs” (Lawrence & Weber, 2011, p. 223). Weyerhaeuser and The Stow Company are two companies that are known for their production of sustainable products and their commitment to social responsibility. Weyerhaeuser has been in the business of making wood products

Toys City Inc Essay

1233 words - 5 pages LGT 3105 Operation Management – Case Assignment 1 (Toys City Inc.) 1. I would have accommodated David Cheung’s vacation request. It is because based on the Critical Path Method (CPM), the network diagram of the work of different audit areas comes as Figure 1, and we can find that the critical path which is the series of activities using the longest time to complete is Activity 1-2-5-7-10-13-15. It means that if there is any

Associated Technologies Case Study (Project Mgt)

823 words - 4 pages activity. Crash Cost Per Time Period or Margin Cost= Marginal Cost = (change in cost)/(change in time) =  (Crash cost - Normal cost)/(Normal time - Crash time) This has to be calculated in line with the project activity list. Secondly finding the current critical path and way to crash the project at the lowest possible cost is the prominent task. To do so,             Identify the critical path in the project net work, mark the critical